Casting work has commenced to build roads in Dh. Kudahuvadhoo
07 April 2022
Updated at: 07 April 2022
The second shipment of additional raw materials and cement
required for the road development project in Dh. Kudahuvadhoo, has been
transported to the island and casting work has begun.
The project was awarded to RDC on 20th September 2021, to be
completed within 450 days.
The project was awarded for MVR 122 million and is being
carried out under the road design and building policy of Kudahuvadhoo.
A total
of 5.85 kilometers of road will be paved and storm water management will be
installed.