Casting work has commenced to build roads in Dh. Kudahuvadhoo

07 April 2022

The second shipment of additional raw materials and cement required for the road development project in Dh. Kudahuvadhoo, has been transported to the island and casting work has begun.
The project was awarded to RDC on 20th September 2021, to be completed within 450 days.
The project was awarded for MVR 122 million and is being carried out under the road design and building policy of Kudahuvadhoo.
A total of 5.85 kilometers of road will be paved and storm water management will be installed.