Asphalt Works Begin on Maamigili Road Project

07 January 2026

Updated at: 07 January 2026

The asphalt works under the Adh. Maamigili Road Construction Project have officially commenced, marking a key milestone in the project’s implementation.
The asphalt works were inaugurated by the Minister of Construction, Housing and Infrastructure, Dr. Abdulla Muththalib, at a ceremony held on the island. The event was attended by the Corporation’s Managing Director, Mr. Ibrahim Nazeem; Maamigili Council President, Mr. Imad Farooq; and other senior officials.
The Maamigili Road Construction Project is currently 89 percent complete. Implemented under the design-and-build model, the project includes the construction and paving of roads, carriageways, and sidewalks. It also encompasses the installation of road gutters, a stormwater management system, speed breakers, road signage, and street lighting.
According to project details, all works except for the pump stations and final asphalt surfacing have already been completed. The project commenced on 26 September 2020 and is being implemented at a total cost of MVR 95,043,314.41.
Upon completion, the project is expected to significantly enhance road safety, accessibility, and overall infrastructure standards for the residents of Maamigili.