ADh. Maamigili Project Updates
31 August 2024
Updated at: 10 September 2024
25th August 2024 - 31st August 2024
Ongoing work includes various activities at different sites. In the casting yard, cable junction rings are being casted, materials are being delivered to work sites, and welding work is focused on making cable junction cover frame nets. The casting yard and site area are being cleaned. On Beach Road, excavation is ongoing, with stormwater pipelines being laid, stormwater junctions being connected, steel grating cover frame rings casted onsite, and backfilling, leveling, and pavement work in progress. At Ameen Magu, excavation and pressure line work are ongoing, with HDPE pipes being laid, sand being filled, and roads cleaned, leveled, and backfilled. Additionally, carpentry work includes making road cleaning brooms and electric socket boards, while the site area is being kept clean.
11th August 2024 - 17th August 2024
In ADh. Maamigli, the current ongoing works include several tasks related to casting and infrastructure development. For casting, activities involve rearranging chemical cement jumbos and other items, making frame nets, filling gaps in stormwater junctions, and setting up for casting. On Beach Road, workers are setting modules for stormwater junctions, leveling the stormwater junctions, and connecting pipes for the stormwater system.
21st July 2024 - 27th July 2024
In ADh. Maamigli, various ongoing projects include the installation of mini curbstones, corner curbstones, and rings on Javaahiru Magu (South). Grating cover installation, frame installation, paving, aligning junction covers, and replacing damaged paving blocks are also in progress. On Rahdhebai Magu, work involves installing corner curbstones, gap filling, key wall alignment next to light posts, and installing key wall modules. Meanwhile, on Bonthijehi Magu, efforts are focused on connecting light posts, paving, curbstone alignment, and replacing damaged paving blocks, along with installing MCB to lights. On Gevehi Magu, paving block filling, connecting lights, and replacing damaged paving blocks are ongoing. At the casting site, activities include cleaning, repairing light modules, sending dry mix to the road, and rearranging the casting yard, as well as delivering materials to work sites. On Ameeni Magu, the work includes connecting and lighting 18 lights, replacing damaged paving blocks, and installing MCB to lights.
30th June 2024 - 06th July 2024
In Javaahiru Magu, activities include ABC laying, installing stormwater tanks, and backfilling. Rahdhebai Magu sees extensive work such as stormwater tank top installation, stormwater junction casting, key wall laying, and gap filling. Additionally, projects on Rahdhebai Magu involve raising junctions, installing stormwater rings, and laying light cables. Other tasks include removing key wall moulds, installing light bases, and corner mini curbstone installation.
23rd June 2024 - 29th June 2024
On Beach Road, key wall work and excavation are underway, alongside the installation of curbstones. Meanwhile, at Rahdhebai Magu, efforts include laying stormwater pipes, repairing stormwater pipes, casting stormwater junctions, and gap-filling corner curbstones. The installation of stormwater tanks is also progressing. Similarly, at Javaahiru Magu, laying light cables and raising stormwater junctions are ongoing.
02nd June 2024 - 08th June 2024
At Javaahiru Magu, keywall laying and manhole leveling work are being carried out, along with other manhole work. Rahdhebai Magu is seeing extensive activity, including the installation and excavation of curbstones, manhole work, laying stormwater pipes, installing key walls, and repairing stormwater pipes. Additionally, excavation for the ABC layer is ongoing. On Beach Road, excavation for the ABC layer is also in progress.
12th May 2024 - 18th May 2024
Along Ameenee Magu, attention is focused on foundational elements such as subgrade preparation. Furthermore, meticulous excavation work is being carried out for the laying of ABC (aggregate base course) and the intricate outfall pipe butt welding and laying, which are crucial for efficient drainage systems. Rahdhebai Magu sees dedicated efforts towards enhancing road aesthetics and safety, with precise excavation for curbstone placement followed by meticulous laying procedures. Similarly, in Gevehi Magu, the focus is on the laying of ABC. Meanwhile, Javaahiru Magu witnesses foundational work with subgrade preparation. Along Beach Road, attention is turned towards enhancing both functionality and aesthetics, with activities ranging from curbstone laying to the installation of keywall structures.
05th May 2024 - 11th May 2024
Rahdhebai Magu is witnessing the laying of essential structures such as keywalls and curbstones, essential for delineating road edges and ensuring structural integrity. Over on Gevehi Magu, the laying of ABC (Aggregate Base Course) is in progress, a crucial step in fortifying road surfaces for increased durability and longevity. Meanwhile, along the Beach Road, similar efforts are focused on the installation of keywalls and curbstones, aimed at enhancing both functionality and aesthetics in this coastal area. Ameenee Magu sees significant groundwork, including excavation for ABC and meticulous subgrading, laying the foundation for robust road construction and longevity.
28th April 2024 - 04th May 2024
Along Rahdhebai Magu, crews are diligently engaged in excavation works to prepare for the laying of curbstones. The elevation and leveling of stormwater junctions are also underway, ensuring effective drainage systems to withstand inclement weather. Meanwhile, along Gevehi Magu, attention turns to utility networks as crews lay cables and undertake repairs on curbstones, bolstering both connectivity and safety. The installation of Aggregate Base Course (ABC) promises durability and resilience for the road's surface. Along the scenic Beach Road, excavation for curbstones, laying of curbstones, and the installation of light bases in the pathways are in progress. The laying of key walls adds structural integrity to the landscape, ensuring stability and longevity. Rahdhebai Magu sees further progress with the laying of curbstones.
21st April 2024 - 27th April 2024
In Adh. Maamigli, significant infrastructure developments are underway in Bonthijehi Magu, Beach Road, and Gevehi Magu. Bonthijehi Magu is seeing the installation of cable junctions and cable pipes, alongside preparations for keywall construction. Additionally, efforts are being made to level manhole junctions and concrete, laying ABC, and raising junctions while ensuring proper leveling. Meanwhile, Beach Road is undergoing curbstone installation, light base installation, excavation for curbstone lines, and laying stormwater pipes, with ongoing repairs to stormwater infrastructure. In Gevehi Magu, similar initiatives include raising junctions, leveling, and stormwater pipe repairs.
07th April 2024 - 20th April 2024
Along Beach Road, attention is devoted to excavating and installing curbstone lines, enhancing both the aesthetics and functionality of the thoroughfare. Additionally, the installation of three light bases promises improved visibility and safety along this coastal route. Meanwhile, on Bonthijehi Magu, essential maintenance work is underway, including the leveling of manhole junctions and concrete surfaces. The replacement of cable junction pipes ensures the seamless operation of utility networks, while the laying of pressure pipes further enhances infrastructure. Backfilling activities complement these efforts, ensuring the stability and longevity of the newly installed components. Notably, the installation of cable junctions and pipes signifies a commitment to modernizing and optimizing utility infrastructure for the benefit of the local community.
31st March 2024 - 06th April 2024
In Ameenee Magu, efforts are focused on road cleaning and backfilling activities around the cable junction area. Concurrently, at Bonthijehi Magu, tasks involve removing concrete covers from manholes, followed by thorough cleaning. Additionally, adjustments and leveling of sewerage manholes are being undertaken to ensure optimal functionality along Bonthijehi Magu. Furthermore, along Gevehi Magu, attention is directed towards junction work.
24th March 2024 - 30th March 2024
In ADh. Maamigli, significant infrastructure improvements are underway on Bonthijehi Magu, Gevehi Magu, and Rahdhebai Magu. On Bonthijehi Magu, efforts include raising the stormwater tank for enhanced drainage capacity, as well as installing grating frames and casting grating on the sides, along with corner curbstone installation, all aimed at optimizing the road's drainage system and improving pedestrian safety. Similarly, on Gevehi Magu, projects involve raising the stormwater tank, installing grating cover frames and cable junction frames, and conducting stormwater replacement work, indicating a comprehensive approach to improving drainage infrastructure and utility services in the area. Meanwhile, on Rahdhebai Magu, backfilling operations are in progress. These initiatives collectively signify a concerted effort to enhance infrastructure and amenities for the residents of ADh. Maamigli.