Dh. Kudahuvadhoo Project Updates
07 September 2024
Updated at: 11 December 2024
01st September 2024 - 07th September 2024
Current work includes stormwater line 2 excavation at Boduburu, installation of stormwater junction type C, laying of UPVC stormwater pipes, road clearance tasks, and setting out with assistance from the island council. On Shaheedh Ali Higun, stormwater works have commenced, involving the excavation of stormwater line 1, installation of type A stormwater junctions, UPVC pipe laying, dewatering, and HDPE pipe butt welding, followed by backfilling and leveling. At Huravee Magu, the team is installing corner curbstones, filling gaps, leveling roads, and working on streetlight cable laying, trenching, and backfilling. Additionally, road clearance and asphalt removal are progressing. In the casting yard, stormwater junction type A and C steel frames are being made, with formwork for stormwater junction type A top under construction and repair, while concrete is provided for stormwater and streetlight foundation teams.
25th August 2024 - 31st August 2024
At Dh. Kudahuvadhoo, various construction works are underway across multiple locations. In Boduburu, excavation for the stormwater line, stormwater junction installation, laying of UPVC stormwater pipelines , backfilling, leveling, and road clearance are ongoing. At Niril Golhi, sidewalk paving, compacting, leveling, corner making, curbstone installation, gap filling, and road leveling are being carried out. On Moonimaa Magu, stormwater work includes excavation, stormwater junction installation, pipeline laying (UPVC and HDPE), butt welding of HDPE pipes, dewatering pipeline work, backfilling, and leveling. Huravee Magu is seeing curbstone installation, chamfer arrangement, gap filling, road leveling, cable junction pipeline rectification, and trenching. At the casting yard, concreting is being done for various stormwater junction types (A, B, C), dewater valve chambers, and stormwater junction tops, along with dry mix provision for the curbstone team and steel frame making for stormwater junction types A and C. Additionally, materials like HDPE pipes are being shifted from the site to the road in Boduburu.
18th August 2024 - 24th August 2024
Extensive work is being carried out across several locations to improve stormwater management and road infrastructure. On Shamsuhdheen Magu, excavation for the stormwater line is in progress, with half catch pits being cast on-site for stormwater junctions (SWJ), followed by backfilling and leveling. Bodu Buru and Boduburu Magu are undergoing road clearance and excavation for stormwater lines, with preparations in place for stormwater work, including the shifting of UPVC pipes and stormwater junctions. At Nirili Goalhi, trenching, curbstone installation, gap filling, and road leveling are taking place, while Moonimaa Magu is focused on stormwater junction installation and pipeline laying, followed by backfilling and leveling. The casting yard is providing critical support, including the casting of stormwater tanks and curbstones, making steel frames for various stormwater tank types, and conducting vehicle maintenance. Additionally, site cleaning and the preparation of dry mix for curbstone teams are ongoing at the casting yard.
11th August 2024 - 17th August 2024
In Dh. Kudahuvadhoo, ongoing work is taking place at multiple locations. On Shamsuhdheen Magu, tasks include excavating for the stormwater line, installing stormwater junctions, laying stormwater pipelines, and performing on-site casting of half catch pits for stormwater junctions, followed by backfilling and leveling. On Bodaavah Magu, trenching, arranging, and installing curbstones, gap filling, backfilling, and road leveling are being carried out, along with corner and tree pit making. On Kariyya Magu, light poles are being installed. At the Casting Yard, concrete is being provided for the stormwater team, while dry mix is prepared for the curbstone team. Additional activities include casting stormwater tanks (types A and B), casting mini curbstones, and making steel frames for the stormwater tanks. Streetlight electric connection work is ongoing, and site cleaning is being maintained to support all these efforts.
04th August 2024 - 10th August 2024
In Dh. Kudahuvadhoo, multiple construction projects are underway across different areas. At Shamsuhdheen Magu, excavation work for stormwater and dewatering lines is being carried out, along with stormwater junction installation and the laying of stormwater pipelines (UPVC pipes,). Similar pipeline work is also happening at Moonimaa Magu, with additional dewatering pipeline work (HDPE pipes) at Shamsuhdheen Magu. Stormwater tank half catch on-site casting is taking place at Rahdhebai Magu, where backfilling and leveling are also in progress. Bodaavah Magu is seeing trenching for curbstone line installation, curbstone chamfer installation, tree pit making, backfilling, and road leveling. Tree pits are also being made at Huravee Magu. Meanwhile, Stormwater Junction type A half catch-pit casting is ongoing at Moonimaa Magu. On Nirili Magu, junction leveling and finishing work, pipeline leveling, backfilling, leveling, and road cleaning are being conducted. Additional site activities include shifting materials to road teams, site cleaning, providing concrete for the stormwater team, making dry mix for the curbstone team, and street light electric connection work.
28th July 2024 - 03rd August 2024
In Dh. Kudahuvadhoo, ongoing work includes excavating for stormwater lines 1 and 2 at Rahdhebai Magu and Shamsuhdheen Magu, as well as for a dewatering line at Shamsuhdheen Magu. Stormwater junction installation and UPVC pipeline laying are taking place at Rahdhebai Magu and Shamsuhdheen Magu, with subsequent backfilling and leveling at these locations. Additional efforts include street light post casting at Huravee Magu, trenching for curbstone installation at Bodaavah Magu and Huravee Magu, and installing curbstone chamfers. Butt welding of HDPE pipes is ongoing at Dhoshimeynaa Magu, with street light cable laying at Kariyya Magu and pole installation at Kaasinjee Hingun. Site cleaning, material shifting to road teams, and the casting of half catch pits at Rahdhebai Magu are also in progress. The work extends to setting street light post foundations, laying HDPE dewatering pipelines, and preparing foundations at Kariyya Magu, all while ensuring consistent site maintenance and cleaning across the various locations.
21st July 2024 - 27th July 2024
In Dh. Kudahuvadhoo, ongoing construction activities include street light cable laying at Kaasinjee Hingun, installing street light poles at Ameenee Goalhi, Sosun Magu, and Aabaadhee Hingun, and casting stormwater tank top sections A and B. Efforts also involve making steel frames for stormwater tanks A and B, butt welding HDPE pipes at Usgandu Magu, Talky Magu, Rahdhebai Magu, and Dhoshimeynaa Magu, and excavating and laying dewatering pipelines at Usgandu Magu, Talky Magu, and Maafay Magu. Additional tasks include installing curbstones with chamfering at Kariyya Magu, tree pit making at Kariyya Magu, backfilling and leveling at multiple locations, and shifting materials to road teams. Site cleaning is conducted regularly, alongside specific tasks such as installing stormwater junctions and trenching for curbstone lines at Huravee Magu.
14th July 2024 - 20th July 2024
Excavation work for stormwater lines 1 and 2 joints is ongoing at Thundee Goalhi, along with laying stormwater pipelines (UPVC pipes) and on-site casting of stormwater junction catch pits. Corner making and trenching existing asphalt for corner making are being carried out at Kariyya Magu, and drymix is being prepared for the corner team. Casting activities include stormwater tanks of types A, B, and top sections, along with the creation of steel frameworks for stormwater tanks type A, B, and C. Materials are being shifted to road teams, and site cleaning work is ongoing. Backfilling and leveling work are also being conducted at Thundee Goalhi and Moonimaa Magu, with additional stormwater pipeline laying and junction installation at Moonimaa Magu. Dewatering pipeline (HDPE pipe ) installation and corner making work are taking place at Kariyya Magu and Kaasinjee Hingun, with continued efforts in preparing drymix and steel frameworks for the stormwater tanks.
07th July 2024 - 13th July 2024
In Dh. Kudahuvadhoo, current works are progressing across multiple sites with a focus on enhancing stormwater management and road infrastructure. At Thundee Goalhi, extensive excavation for Stormwater line 1 is underway, involving the laying of UPVC stormwater pipelines and the installation of stormwater junctions. Concurrently, corner making and trenching of existing asphalt are being executed at Kaasinjee Hingun, complemented by dry mix preparation and the casting of stormwater tanks, types A and B, including their top sections. Similar efforts are ongoing at Kariyya Magu, where corner making and trenching works are conducted alongside HDPE pipe welding and dewatering pipeline laying. Additionally, on-site casting of stormwater junction catch pits is in progress. Across all locations, steel framework for stormwater tanks is being fabricated, materials are being shifted to road teams, and comprehensive site cleaning is maintained. Furthermore, CSR activities are performed as per police requests, ensuring the community benefits from these infrastructure improvements.
30th June 2024 - 06th July 2024
In Dh. Kudahuvadhoo, extensive work is ongoing to improve stormwater management and road conditions. Excavation for Stormwater Line 3 is being carried out at Saimaa Hingun, with stormwater pipelines being laid and junction catch pits being cast on-site at Fareedhee Magu. Various types of stormwater tanks (A, B, and C) and their top sections are being cast, along with the preparation of steel frameworks for these tanks. Additional tasks include shifting materials from the harbor to the site, cleaning and leveling roads, making foam work for stormwater tanks, and rearranging the site area. At Fareedhee Magu Line 3, half catch-pits are being cast, and paving blocks are being halved, separated, and palletized. Excavation for Stormwater Line 1 is also underway at Thundee Goalhi, where stormwater pipelines and junctions are being installed. Corner making is in progress at Rahmaanee Hingun, supported by dry mix preparation for the corner team. Material shifting to road teams and continued steel framework preparation for stormwater tanks are also part of the ongoing efforts.
23rd June 2024 - 29th June 2024
Excavation work for Stormwater Line 3 is in progress at Fareedhee Magu, along with the installation of Stormwater Junction Type C and the laying of a 200mm UPVC stormwater pipeline. Backfilling and leveling activities are also ongoing at Fareedhee Magu. Sidewalk paving work is being carried out at Sosan Magu, including corner finishing and curbstone on-site casting. Additionally, sidewalk preparation for paving is underway at Rahmaanee Magu. The construction efforts include the casting of Stormwater Tanks A, B, and C, as well as their top sections, and the fabrication of steel frameworks for these tanks.
02nd June 2024 - 08th June 2024
Excavation and backfilling work for stormwater systems are being conducted at Fareedhee Magu and Saimaa Hingun, where UPVC and HDPE pipelines are being installed, with HDPE pipe butt welding also in progress. Stormwater junction installations are taking place at Fareedhee Magu and Saimaa Hingun, with extensive work on casting stormwater tanks of types A, B, and C, along with their top sections. These tasks are complemented by sidewalk preparation and paving at locations including Muhidheen Magu, Sosan Magu, and Aabadhee Hingun, with curbstone installation and corner finishing work being done at Husainee Hingun. Road clearance and cleaning efforts are ongoing, particularly at Fareedhee Magu, Nirili Goalhi, and Muhidheen Magu, where damaged paving blocks are also being shifted. CBJ frame removal and border making are taking place at multiple sites. Additionally, the team is engaged in CSR activities, such as removing pavement blocks and leveling in front of the mosque, as per council requisition for Eid celebrations. Other tasks include making steel framework and foam work for stormwater tanks, casting culvert joints, unloading deformed bars, and delivering materials and equipment to various sites to support ongoing operations.
26th May 2024 - 01st June 2024
At Fareedhee Magu, the work includes excavating for stormwater management, installing stormwater junctions, laying 200mm UPVC stormwater pipelines, casting catch pits on-site, and performing backfilling and leveling. Additionally, stormwater tanks of types A1, B, and C, as well as Cable Junction type B rings, are being cast. Steel framework and foam work for the tanks are being constructed, and the site is undergoing cleaning and rearranging, with paving blocks being palleted. At Kaasinjee Hingun, on-site casting of light post foundations, tree pits, and curbstones is taking place, along with corner finishing work. Sidewalk preparations for paving are underway at Muhidheen Magu and Nirili Goalhi, with sidewalk finishing work also occurring at Nirili Goalhi.
19th May 2024 - 25th May 2024
Fareedhee Magu is witnessing on-site casting of catch pits, backfilling, and leveling activities, alongside excavation work for stormwater systems and the laying of UPVC pipes, demonstrating a comprehensive approach to drainage management. Additionally, the installation of Stormwater tank type A underscores efforts to improve water retention and flood prevention measures. Meanwhile, Muhidheen Magu sees preparations for sidewalk paving and the laying of boundary quay walls, along with the installation of street light cables. Notably, casting works for Stormwater tanks and cable junctions are in progress, accompanied by road leveling efforts and the preparation of paving blocks.
12th May 2024 - 18th May 2024
Along Fareedhee Magu, work focuses on stormwater management with excavation for installing Stormwater tank type C, followed by backfilling and leveling. The laying of UPVC pipes ensures durable water transport, while the installation of Stormwater tank type A and HDPE Pipe 110mm butt welding addresses comprehensive drainage needs. Dewatering pipelines are also being laid to enhance water resilience. Meanwhile, Kurivaa Hingun is being prepared for sidewalk paving to improve pedestrian safety and accessibility. Boundary walls are being constructed while the completion of sidewalk paving is ongoing.
05th May 2024 - 11th May 2024
Along Bodaavah Magu, the groundwork for improved stormwater management is evident through excavation works, paving the way for the installation of stormwater junctions. Concurrently, catch pit on-site casting enhances drainage efficiency, crucial for mitigating flood risks during inclement weather. Kurivaa Hingun is undergoing sidewalk paving preparations, signaling a commitment to pedestrian safety and accessibility, with subsequent paving works promising enhanced walkability. Similarly, Kaasinjee Hingun sees progress with the installation of curb lines, essential for delineating road edges and ensuring orderly traffic flow. Fareedhee Magu witnesses focused efforts on stormwater infrastructure, with excavation works underway for stormwater lines and the installation of type C stormwater junctions, underscoring the island's commitment to comprehensive infrastructure upgrades.
28th April 2024 - 04th May 2024
Along Bodaavah Magu, work is carried out for laying the groundwork for the installation of stormwater junctions and catch pits. Road clearance efforts ensure unimpeded progress, paving the way for efficient stormwater management systems. In Balleedhandu Hingun, paving work is ongoing. Simultaneously, excavation works for dewatering pipelines signify a commitment to mitigating water-related challenges. Meanwhile, along Kaasinjee Hingun, the installation of curbstones adds both functionality and aesthetic appeal to the streetscape. Lastly, at Nirili Goalhi, meticulous attention to detail is evident as corner finishing works enhance the visual appeal and safety of the thoroughfare.
21st April 2024 - 27th April 2024
Bodurasgefaanu Magu is currently undergoing sidewalk paving and corner paving work, with a focus on gap filling and pavement finishing to ensure smooth and safe pedestrian pathways. Similarly, Ameenee Goalhi is seeing sidewalk corner paving and pavement finishing activities to enhance pedestrian accessibility and safety. In Aabaadhee Hingun, efforts are directed towards tree pit making, contributing to the greening and beautification of the neighborhood. Meanwhile, Bodaavah Magu is the site of stormwater pipeline laying, stormwater junction installation, and stormwater catch pit on-site casting, essential for effective drainage management. Sosun Magu is undergoing street light cable laying to improve visibility and safety during the night, while Nirili Goalhi and Baleedhandu Hingun are both undergoing sidewalk preparation and paving works, further enhancing pedestrian infrastructure across Dh. Kudahuvadhoo.
07th April 2024 - 20th April 2024
Along Husainee Hingun, initiatives include trenching for street light cables, laying these cables, and subsequent backfilling and leveling activities. Simultaneously, sidewalk paving efforts are underway, enhancing pedestrian accessibility and safety in the vicinity.
In Nirili Goalhi and Bodurasgefaanu Magu, the focus is on sidewalk paving, aiming to create pedestrian-friendly environments conducive to community engagement and mobility. Meanwhile, Muhihdheen Magu and Ameenee Goalhi witness tree pit making and sidewalk paving projects, respectively, further enhancing the greenery and walkability of these areas. Lastly, Sosun Magu undergoes tree pit making as well, enriching the urban landscape and promoting environmental sustainability.
31st March 2024 - 06th April 2024
Along Fareedhee Magu, essential tasks include excavating for stormwater management, rectifying cable junctions, and conducting backfilling and leveling work. Simultaneously, the installation of stormwater junction type A1 tops and steel grating is advancing to bolster drainage systems. On Husainee Hingun, efforts focus on trenching existing asphalt to facilitate corner making, while tree pit creation enhances greenery along Balleedhandu Hingun. Ameenee Goalhi sees the completion of tree pit finishing, along with ongoing trenching, backfilling, and corner making endeavors to optimize traffic flow and safety. Meanwhile, Bodu Rasgefaanu Goalhi's landscape is being enhanced through the finalization of tree pit finishing work.
24th March 2024 - 30th March 2024
In Dh. Kudahuvadhoo, various projects are underway across different areas. In Fareedhee Magu, efforts are focused on improving drainage infrastructure, with activities such as backfilling and leveling, excavation for storm water systems, installation of storm water junctions, and laying storm water pipeline pipes. On Kurivaa Hingun, work is being done to finish tree pits, likely as part of landscaping efforts to beautify the area and provide greenery. Sosun Magu sees excavation of existing asphalt to facilitate corner making, indicating potential road layout adjustments for improved traffic flow and safety. Similarly, on Aabaadhee Hingun, excavation of existing asphalt is taking place for corner making, likely as part of road improvement projects. In Husenee Hingun, activities involve excavation for curbline installation, followed by the installation of curbline structures. Backfilling and leveling works are also in progress to ensure the road surface is restored and leveled properly. Lastly, on Balleedhandu Hingun, finishing works for tree pits are being carried out.
17th March 2024 - 23rd March 2024
Road development activities are currently underway on three different roads: Bodurasgefaanu Magu, Fareedhee Magu, and Sosun Magu. At Bodurasgefaanu Magu, the primary focus is on backfilling and leveling to ensure proper groundwork preparation. Fareedhee Magu is undergoing stormwater pipeline work, involving excavation, pipe laying, junction installation, and HDPE pipe welding. Additionally, there is work related to dewatering HDPE pipes. Meanwhile, Sosun Magu is undergoing enhancements to its infrastructure, including trenching existing asphalt for finishing road corners and completing tree pits.