Lh. Hinnavaru Project Updates

31 August 2024

Updated at: 10 September 2024

25th August 2024 - 31st August 2024
Several construction activities are currently in progress across various locations. Paving blocks are being laid at Ijuthimaaee Magu and Road 02. Stormwater (SW) metal frames are being made at Kaneeru Magu, and SW elevation work is ongoing at Ijthimaaee Magu and Road 1. Additionally, curbstone laying is being carried out at Road 09, while tree pits are being installed and finished at Roads 05 and 06. Other tasks include corner curb installations at Roads 05 and 06, SW repair work at Kaaminee Magu, re-palletting, and the installation of street lights at Ijthimaaee and Kaaminee Magu. Soak pits are also being installed at Road 01. 
18th August 2024 - 24th August 2024
Ongoing work includes keywall laying at Ijuthimaaee Magu, where SW catchpit elevation and curbstone junction finishing, along with border making, are also being carried out. Curbstone laying is progressing at Road 02, Road 05, and Road 06, with tree pit installation underway at Ijthimaaee Magu, Road 02, and Road 05. Additionally, soakpit laying and pipe crossing have been completed at Road 01. SW metal frame making is taking place at Ijthimaaee Magu and Kaneeru Magu, with consistent efforts in various areas to advance construction and infrastructure development.
11th August 2024 - 17th August 2024
In Lh. Hinnavaru, various ongoing works are being carried out across different locations. Keywall laying is actively taking place at Dhooriya Magu, Daizy Magu, and Ijthimaaee Magu. Additionally, stormwater catchpit elevation is being performed at Ijthimaaee Magu and Kaaminee Magu, with stormwater catchpit finishing also underway at Kaaminee Magu. On Road 02, corner curbs are being laid, while curbstone junction finishing and border making are ongoing at Lhaithumaa Magu, Road 02, and Ijthimaaee Magu. Soakpit laying and pipe crossing are being executed at Road 01, and treepit installation is taking place at Ijthimaaee Magu. Furthermore, casting activities are ongoing as part of the broader construction efforts. 
04th August 2024 - 10th August 2024
In Lh. Hinnavaru, several construction activities are ongoing. Keywall laying is being carried out at Dhooriya Magu, along with stormwater catchpit elevation at Ijthimaaee Magu. Curbstone installation is taking place on Road 02, and corner curb laying is also being done on the same road. Additionally, culvert frame making is in progress, and street lights are being installed on Road 4 and Road 8. On Lhaithumaa Magu, cable junction finishing and border making are being completed.
28th July 2024 - 03rd August 2024
In Lh. Hinnavaru, keywall laying is underway at Dhooriya Magu, alongside stormwater catchpit elevation work at Road 04. Curbstone installation is being carried out at Kaaminee, Ijthimaaee Magu, and Road 02. Paving blocks are being laid at Kaneeru Magu and Daizy Magu, with keywall casting also ongoing at Dhooriya Magu. Additionally, pipe crossing is being installed at Road 2, stormwater catchpit cover finishing work is progressing at Lhaethuma Magu, and corner curb laying is taking place at Road 02.
21st July 2024 - 27th July 2024
In Lh. Hinnavaru, keywall laying and cable junction elevation are taking place at Dhooriya Magu. The stormwater catchpit elevation is ongoing at Daizy Magu, and pipe crossing work is being conducted at Road 2. Current ongoing work includes laying paving blocks and finishing the cable junction border at Dhooriya Magu, as well as pipe crossing at Road 2. Additionally, paving block laying and cable junction border finishing are in progress at Dhooriya Magu and Nooraanee Magu. The stormwater catchpit elevation is underway at Road 4, with continued pipe crossing at Road 2.
14th July 2024 - 20th July 2024
In Lh. Hinnavaru, several construction activities are currently underway. These include casting soakpits and curbstones, paving cut pieces at Nooraanee Magu, and stormwater catchpit elevation at Daizy Magu. At Dhooriya Magu, cable junction border finishing work and keywall laying are in progress, along with the elevation of cable junctions. Additional tasks include casting soakpit covers, stormwater catchpit covers, and curbstone palleting.
30th June 2024 - 06th July 2024
In Lh. Hinnavaru, a series of construction and infrastructure projects are currently underway. These include curbstone and soakpit casting, as well as paving block laying at Nooraanee Magu. The cable junction border elevation is being carried out at Kaaminee Magu and Road 8, with stormwater catchpit elevation also taking place at Nooraanee Magu. The work continues with curbstone, culvert, soakpit cover, and stormwater catchpit cover casting, alongside paving block laying at Road 7×15 and Kaneeru Magu. Additionally, ongoing tasks involve culvert casting, cut piece laying, and drymix laying at Nooraanee Magu, cable junction elevation at Madharusee Magu, and stormwater catchpit elevation at various locations including Nooraanee Magu.
23rd June 2024 - 29th June 2024
Curbstone installation is in progress at Road 1, while paving cut pieces are being laid at Nooraanee Magu. Cable junction elevation work is being carried out at Kaaminee Magu, alongside soakpit casting. Paving work continues at Nooraanee Magu, complemented by curbstone border elevation efforts at Kaaminee Magu. Stormwater catchpit elevation is also taking place at Nooraanee Magu. Additionally, curbstone casting and soakpit cover casting are underway. Preparations for further curbstone casting are in progress, ensuring the successful completion of these essential infrastructure improvements.
02nd June 2024 - 08th June 2024
Curbstone installation is underway at Road 1, accompanied by paving works at Road 4. At Dhooriyaa Magu, the CBJ frame is being removed and border making is in progress. Stormwater casting work is being conducted at Nooraanee Magu, which also sees paving works, CBJ frame removal, border making, and paving cut piece laying. Additionally, CBJ border making is occurring at Kaaminee Magu, along with stormwater catchpit elevation at Nooraanee Magu. Excavation for curbstone installation is also taking place at Road 1.  
26th May 2024 - 01st June 2024
Curbstone installation is ongoing at Road 1, while paving works are being carried out at Road 4. At Dhooriyaa Magu, extensive work includes the demolition and finishing of cable junctions, the elevation of cable junctions, the removal of cable junction frames, and border making. Additionally, storm water management efforts are underway with finishing work and casting work at Road 8.
12th May 2024 - 18th May 2024
Along Road 4, attention is being given to tree pit finishing work, ensuring both aesthetic appeal and environmental sustainability, while keywall installations promise structural integrity and longevity. On Nooraanee Magu, efforts are underway to finalize cable junction border finishing works. Road 8 is seeing work such as dry mix laying, tree pit installations, stormwater finishing works, and paving. Meanwhile, on Road 10, the elevation of stormwater catchpits underscores a proactive stance towards flood prevention.
05th May 2024 - 11th May 2024
In the bustling community of Lh. Hinnavaru, infrastructure upgrades are shaping the landscape, with particular focus on Road 4. Here, efforts are concentrated on enhancing the road's structure with the installation of curbstones and mini curbs, ensuring safer and more defined pathways for residents. Meanwhile, over on Road 8, attention is turned to elevating cable junctions, crucial for optimizing connectivity, alongside ongoing paving works aimed at enhancing the road surface for smoother travel experiences. Nooraanee Magu is witnessing a flurry of activity, including the elevation of cable junctions to streamline telecommunications infrastructure, while concurrent stormwater resurfacing works promise improved drainage efficiency. Notably, the meticulous casting of borders around cable junctions underscores the attention to detail in this comprehensive overhaul. Road 10 sees a focus on stormwater catchpit elevation, a pivotal step in mitigating flood risks and ensuring effective drainage management across the area.
28th April 2024 - 04th May 2024
Along Road 8, progress unfolds as keywall laying sets the foundation for enhanced stability, while efforts to elevate cable junctions are underway to mitigate potential hazards. Concurrently, paving works are in full swing, promising smoother journeys for commuters traversing this vital artery. Meanwhile, along Road 10, the streets of Daizy Magu are set to shine brighter with the ongoing installation of streetlights, illuminating pathways for increased safety and visibility. Simultaneously, on Dhooriya Magu, the elevation of cable junctions takes precedence.
21st April 2024 - 27th April 2024
In Hinnavaru, significant progress is being made on various infrastructure projects along Road 8 and Road 10. Road 8 is currently undergoing keywall laying and cable junction elevation work, while also seeing the casting of light post foundations. Meanwhile, Road 10 is witnessing cable junction elevation efforts alongside paving work. These endeavors aim to enhance the road network and ensure smoother transportation for residents and visitors alike. Additionally, in Nooraanee Magu, the installation of street lights is underway, further contributing to the area's safety and accessibility. 
07th April 2024 - 20th April 2024
Along Road 08, activities include the meticulous paving of the thoroughfare, alongside the setup of tree pits to enrich the urban greenery. Elevating cable junctions ensures efficient utility management, while the installation of tree pits enhances the area's aesthetic appeal and ecological balance. Moreover, the laying of corner curbs at the intersection of Road 08 and Dhooriya Magu promises improved traffic flow and safety measures.
Similarly, along Road 10, progress abounds with the elevation of cable junctions and the meticulous finishing of tree pits. Paving works along the road and the careful completion of light post foundations further signify a commitment to quality and functionality. Notably, the laying of corner curbs at the intersection of Road 10 and Nooraanee Magu underscores efforts to optimize traffic management and enhance pedestrian safety.
31st March 2024 - 06th April 2024
Along Road 8, the laying of curbstones is currently underway. Simultaneously, efforts are being directed towards the establishment and refinement of tree pits to augment the area's aesthetic appeal while ensuring environmental sustainability. Similarly, along Road 10, the installation of keywalls is progressing to reinforce structural integrity, followed by the placement of paving blocks. Moreover, activities involving the demolition and elevation of cable junctions are underway.
24th March 2024 - 30th March 2024
In Hinnavaru, ongoing construction activities this week include Road 8 and Road 10. Along Road 8, the focus is on laying curbstones, a crucial step in delineating road edges and ensuring pedestrian safety. Meanwhile, on Road 10, efforts are concentrated on laying paving blocks, a process that involves the installation of durable surfaces for vehicles and pedestrian traffic. Additionally, tasks such as cable junction elevation and setting retaining walls are underway, indicating comprehensive measures to improve drainage and structural integrity along the roads.
17th March 2024 - 23rd March 2024
At Nooraanee Magu, the focus is on improving road surfaces through paving work, ensuring smoother and safer travel for residents and commuters. Additionally, attention is directed towards cable junction border works, as well as maintaining and upgrading utility networks. Concurrently, dry mix laying activities are in progress, further enhancing the durability and quality of road surfaces. Cable junction border casting is also being carried out to reinforce infrastructure. Furthermore, road watering and leveling covering 188 meters are ongoing, contributing to the maintenance of road quality and safety standards.
On Road 10, curbstone laying activities are underway, aimed at enhancing pedestrian pathways and delineating road edges. Additionally, dry mix laying is being conducted to improve road surfaces and ensure long-term durability.
In Daizy Magu, efforts are focused on road watering and leveling, underscoring a commitment to maintaining road quality and safety standards in the area.