M. Mulak Project Updates

24 March 2024

30th June 2024 - 06th July 2024
On Chaandhaneemagu, paving cut pieces are being laid, and cable junction elevation is in progress. Alikileygefaanumagu sees various activities, including curb installation, street light foot casting, dry mix laying on corner curbs, and backfilling. The casting yard is busy with the production of big and small curbstones and stormwater catch pits, while on-site welding involves stormwater catch pit rings and tank top mould repairs. Additionally, excavation and paving work, including gap filling with dry mix, are underway on Alikileygefaanumagu, alongside preparations for street light foot foundation work. Mulahmaa Hingun features cable junction border casting and paving activities, including re-arranging paving blocks on Huseyneemagu. In carpentry, shuttering for street light foundations and key walls is being constructed. 
23rd June 2024 - 29th June 2024
In the casting yard, large curbstones are being cast, aggregates are transferred from damaged to new bags, and materials are being re-organized. The welding of the stormwater tank catchpit ring is ongoing, and raw materials such as cement, aggregates, and C sand are being transported from the harbour to the site. Excavation and crossing pipe laying are progressing at Alikileygefaanumagu, along with curbstone installation and stormwater pipeline excavation. At Chaandhaneemagu, paving work is being conducted, along with preparations for cable junction elevation and keywall laying, as well as the installation of corner curbs. Additional efforts at the site include street light cable laying, road clearance, and leveling, and the removal and transfer of excess sand. The site also focuses on welding activities and various casting yard tasks, including casting both large and small curbstones. Specific to Chaandhaneemagu, cable junction border casting and finishing work are being conducted.
02nd June 2024 - 08th June 2024
Paving work is being conducted on Alikileygefaanu Magu, along with stormwater tank and pipe installation. On Huseynee Magu, CBJ elevation and finishing work are underway. The site also sees the casting of hollow blocks and large curbstones at the casting yard, welding work for key wall shuttering, and carpentry work for shuttering the stormwater top level. Chaandhanee Magu is a hub of activity with curb installation, paving work, street light installation, key wall laying, and welding work for making the stormwater tank ring.
26th May 2024 - 01st June 2024
On Alikileygefaanu Magu, activities include corner curb installation, paving work, storm water tank and pipe installation, cable junction crossing pipe laying, and dry mix laying on the pavement. Additionally, welding and carpentry work are being conducted for keywall and storm water catchpit shuttering. Finishing work on corner curbs is also underway. On Mulamma Hingun, the top level of the storm water tank is being cast, while Huseynee Magu is seeing cable junction elevation and street light installation. Street light installation and cable laying is ongoing in Chaandhanee Magu. Furthermore, hollow blocks and large curbstones are being cast at the site, with ongoing welding and carpentry work. 
19th May 2024 - 25th May 2024
At Husaynee Magu, initiatives include the re-arrangement of paving blocks, casting of CBJ borders, and road cleaning and leveling, alongside the efficient transfer of excess sand from roads to designated sites, ensuring smoother and safer travel routes. Meanwhile, Alikileygefaanu Magu sees significant progress with paving and curb installation works, along with meticulous attention to detail in finishing corner curbs. In Chaandhanee Magu, efforts are focused on addressing leakage issues in stormwater tanks and conducting onsite casting for optimal water management solutions. Additionally, at Mulamma Hingun, the installation of stormwater tanks and pipes, coupled with top-level casting, signifies a proactive approach to strengthening essential utilities.
12th May 2024 - 18th May 2024
Along Ameenee Magu, work focuses on subgrade preparation, laying ABC (aggregate base course), and installing outfall pipes for efficient drainage. Rahdhebai Magu sees efforts to enhance road aesthetics and safety with curbstone placement. Gevehi Magu focuses on laying ABC. Javaahiru Magu undergoes subgrade preparation. Along Beach Road, activities include curbstone laying and keywall installation.
05th May 2024 - 11th May 2024
Along Chaandhanee Magu, comprehensive efforts are underway, including excavation work for stormwater tanks and pipe installations, alongside the enhancement of the stormwater network and the laying of outfall pipes. Concurrently, the installation of stormwater tanks and pipes promises improved drainage systems, crucial for mitigating flood risks. Huseynee Magu is witnessing significant upgrades, with attention to detail evident in light foot casting and meticulous paving works. Road clearance initiatives are enhancing accessibility, while elevation work on cable junctions’ underscores efforts to modernize telecommunications infrastructure. Alikilegefaanu Magu sees progress with curb and corner curb installations. Meanwhile, Mulammaa Hingun and Asaree Hingun are undergoing curb installations and light foot finishing work, respectively, further enhancing pedestrian pathways and road aesthetics. Lastly, Kaneyson Hingun sees similar efforts in light foot finishing, emphasizing the island's commitment to ensuring safe and well-maintained walkways across its thoroughfares.
28th April 2024 - 04th May 2024
Along Chaandhanee Magu, crews are diligently engaged in excavation works, laying the groundwork for the installation of stormwater tanks and pipes, vital components in mitigating water-related issues. Meanwhile, over at Huseynee Magu, attention turns to enhancing road integrity and safety. The installation of corner curbs and the laying of key walls, along with meticulous road clearance efforts, pave the way for paving work. In Mulammaa Hingun, the focus shifts to pedestrian infrastructure, with crews diligently executing light foot casting works to ensure safe pathways for pedestrians. Lastly, at Alikilegefaanu Magu, curbstone installation work is ongoing.  
21st April 2024 - 27th April 2024
In Chaandhanee Magu, paving work is in progress, accompanied by excavation and stormwater pipe laying activities aimed at enhancing drainage systems. Additionally, efforts are underway to re-install stormwater tanks and pipes to ensure efficient water management. In Huseynee Magu, keywall laying is ongoing alongside paving work, cable junction crossing pipe laying, and curb installation, all contributing to the neighborhood's infrastructure upgrade. Furthermore, cable junction elevation work is being carried out to enhance the reliability of the electrical network. In Asaree Hingun and Kaneysan Hingun, the installation of light foot castings is underway, adding to the area's safety and accessibility measures. 
07th April 2024 - 20th April 2024
Along Chaandhanee Magu, meticulous paving work is underway, aimed at enhancing the accessibility and aesthetics of the thoroughfare. Onsite casting of stormwater top-level and welding activities ensures robust utility infrastructure, complemented by the installation of stormwater tanks and laying of pipes to mitigate flooding risks. Simultaneously, the removal of shuttering and backfilling activities signifies progress toward completing these crucial projects.
In Huseynee Magu, attention is focused on fortifying the landscape with keywall laying, offering structural stability. The casting of light footings enhances pedestrian safety and accessibility, aligning with efforts to create a welcoming environment. Additionally, sidewalk paving endeavors promise to further enhance the pedestrian experience, fostering a sense of connectivity and community engagement.
31st March 2024 - 06th April 2024
Along Huseynee Magu, a variety of infrastructure development tasks are currently underway. This includes laying paving blocks to establish durable and visually appealing pathways, as well as filling curb gaps to ensure accessibility and safety for pedestrians. Backfilling operations are also in progress to provide stability and support to the surrounding areas. Additionally, keywalls are being implemented to reinforce structural integrity and prevent erosion along the thoroughfare. Meanwhile, in Chaandhanee Magu, the installation of a stormwater tank is being conducted to manage and mitigate the impact of stormwater runoff, emphasizing environmental sustainability and infrastructure resilience in M. Mulak.  
24th March 2024 - 30th March 2024
In M. Mulak, various infrastructure projects are progressing across different areas, including Sosun Magu, Huseynee Magu, Ameenee Magu, and Chaandhanee Magu. On Sosun Magu, efforts are focused on road maintenance with tasks such as cleaning and leveling, aiming to improve the overall condition and accessibility of the road. In Huseynee Magu, several tasks are underway, including laying paving cut pieces, installing large curbstones, laying CBJ crossing pipes, installing corner curbs, and casting footings for street lights. Additionally, backfilling and cleaning activities are being conducted, indicating the completion of previous tasks and preparation for subsequent phases. Ameenee Magu is undergoing excavation work and stormwater (SW) pipe laying, suggesting upgrades to the drainage system for better water management. Furthermore, preparations for casting the SW top-level are in progress. In Chaandhanee Magu, excavation work is underway for the installation of a stormwater tank.
17th March 2024 - 23rd March 2024
At Sosun Magu, the focus is on stormwater management with the installation of a stormwater tank, laying of stormwater pipes, and backfilling works to ensure effective drainage. Additionally, road cleaning activities are being carried out to maintain cleanliness and ensure the smooth functioning of the road.
In Huseynee Magu, paving work is carried out to improve road surfaces, backfilling work to stabilize the ground, and the laying of cable junction cross pipes to reinforce utility networks. Furthermore, streetlight post installation aims to enhance visibility and safety for pedestrians and commuters, while cable junction elevation works are underway.
Meanwhile, at Ameenee Magu, efforts are focused on excavating and relocating a stormwater tank to improve its functionality and optimize its placement within the area.
  • Share:

Related News