N. Holhudhoo Project Updates

24 March 2024

07th April 2024 - 20th April 2024
Along Tulip Hingun, a flurry of activity includes excavation and meticulous backfilling, along with the installation of crucial junctions and laying and connecting of pipes. Over at Meyna School, a comprehensive overhaul is in progress, featuring the alignment of turf ground, the manufacturing and installation of a new entrance gate, and extensive excavation to facilitate drainage for the football ground. Concurrently, junctions are being installed and pipes are laid to ensure efficient water management. Meanwhile, on Chaandhanee Hingun, excavation and backfilling activities complemented by the installation of junctions and pipes. Moreover, installation of stormwater junctions are underway. 
31st March 2024 - 06th April 2024
In N. Holhudhoo, along Tulip Hingun, the construction process begins with excavation and backfilling operations, laying the groundwork for subsequent phases. Following this initial step, pipe laying and junction installment follow suit. Once the pipes are securely in place, meticulous backfilling ensues, ensuring stability and integrity for the infrastructure. Finally, road clearance activities are undertaken, prioritizing accessibility and safety for the community. This coordinated effort aims to enhance the area's infrastructure, facilitating smoother transportation and improving overall living standards.  
24th March 2024 - 30th March 2024
Construction efforts along Tulip Hingun are progressing well, with various tasks aimed at enhancing the area's infrastructure. Excavation work is currently underway to facilitate pipe laying, particularly for storm water systems and junctions. Following this, backfilling operations will be conducted to ensure the stability and functionality of the newly installed pipes.
17th March 2024 - 23rd March 2024
Various urban development projects are currently underway across different areas to enhance infrastructure and urban amenities. In Unimaa Magu, the primary focus is on improving junctions through the construction of a new one. Meanwhile, at Madharusaa Magu, efforts are directed towards clearing roads to ensure accessibility and safety for pedestrians and vehicles. In Tulip Hingun, attention is shifted to stormwater management, with ongoing excavation work for a 12-meter stormwater pipeline. Additionally, efforts are being made to clear stormwater excavation areas and backfill them, ensuring the effective management of the water drainage system.