N. Holhudhoo Project Updates

17 August 2024

Updated at: 26 August 2024

11th August 2024 - 17th August 2024
In N. Holhudhoo, various activities were carried out across different sites. Materials were delivered to work sites, and on-site tasks included curbstone deshuttering, mould cleaning, and oiling, followed by curbstone and C-type junction casting. At Lainoofaru Magu, stormwater junctions were extended and cast, with the installation of Stormwater junctions and pipes, followed by backfilling and road clearance. To facilitate curbstone work, a tree was cut down and the area cleared at Kaaminee Hingun. Carbstone casting, mould repairs, C-type junction foam works, and shuttering cleaning were ongoing. In Chaandhanee Magu, materials were delivered, and centerline and level marking were done. Stormwater junction and pipe network installation were ongoing, along with backfilling, road clearance, and relocating casted curbstones. 
28th July 2024 - 03rd August 2024
In N. Holhudhoo, ongoing work at Moosakaleyfaanu Magu includes excavation, backfilling, and the installation of stormwater junctions and pipes. Activities such as stormwater junction deshuttering, covering, backfilling, foam works, reinforcement, and casting are being carried out. Material deliveries and pipe relocations are also in progress, along with extending the stormwater junction. C-Type junction foam works, reinforcement, casting, and backfilling are being conducted as well. In Lainoofaru Magu, work includes stormwater junction deshuttering, covering, backfilling, and network installation. Curbstone network installation, road clearance, and stormwater pipe installation are also ongoing. Additionally, material deliveries continue, along with the installation and casting of stormwater junctions and curbstone networks, followed by backfilling.
21st July 2024 - 27th July 2024
In N. Holhudhoo, materials are being delivered to Meyna School and Moosakaleyfaanu Magu. On Hassankaleyfaanu Magu, backfilling, curbstone installation, filling gaps between curbstones, and road cleaning are taking place. On Moosakaleyfaanu Magu, excavation, backfilling, pipe installation, and road clearance are ongoing. At Meyna School, shuttering sets on one of the benches were fixed, casted, and deshuttered, and gaps were filled in the curbstones from the mini football ground. Current works include material delivery to Hassankaleyfaanu Magu and Moosakaleyfaanu Magu, and shifting waste materials from Unimaa Magu to the site. On Hassankaleyfaanu Magu, curbstone installation, backfilling, and road clearance are ongoing. On Moosakaleyfaanu Magu, activities include excavation, backfilling, stormwater junction installation and extension, pipe installation, and road cleaning. Additionally, two loads of concrete have been delivered to Moosakaleyfaanu Magu for further works including excavation, backfilling, stormwater junction installation and extension, deshuttering, covering, and backfilling. On Tulip Hingun, stormwater junction ring casting is in progress. On site, there are ongoing C-type junction foam works, reinforcement works, and casting. Shuttering sets on the C-type junctions have been removed, the casting bed has been cleaned, curbstone casting is ongoing, and curbstone molds have been cleaned, oiled, and arranged on the casting bed. Concrete is being mixed for stormwater junction extension works.
14th July 2024 - 20th July 2024
In N. Holhudhoo, several ongoing construction and maintenance activities are underway. At Hassankaleyfaanu Magu, curbstone delivery, excavation for curb installation, curbstone installation, backfilling, and road clearance are in progress. Additionally, materials are being delivered to both Hassankaleyfaanu Magu and Meyna School. In Madharusa Magu, stormwater junction formworks, reinforcement works, casting, deshuttering, and covering are being carried out. The remaining curbstones, junctions, pipes, and waste materials have been shifted back to the RDC site. At Meyna School, ground preparation and paving block laying near the benches are ongoing.
30th June 2024 - 06th July 2024
Various construction works are currently underway, primarily focused on Hassankaleyfaanu Magu. These activities include material delivery to the site, excavation, backfilling, Stormwater pipe installation, Stormwater junction installation, and road clearance. Additionally, at the intersection of Hassankaleyfaanu Magu and Mohamed Raashidh Hingun, Stormwater junction foam works and reinforcement works are in progress. At the intersection of Hassankaleyfaanu Magu and Moosaakaleyfaanu Magu, similar efforts are being made with SW junction foam works, reinforcement, and casting. Specific tasks completed at the school include finishing the center bench concrete and rearranging the wooden slabs.  
23rd June 2024 - 29th June 2024
At Meyna School, efforts focused on renovating the bench tables, which included deshuttering the tables, finishing foam works, and reinforcement works on the center table, as well as completing the foam works on the center table legs and casting them. On Chaandhanee Magu, the casting of cable junction covers was carried out. Additionally, on Hassan Kaleyfaanu Magu, excavation work was conducted in preparation for curb installation.
02nd June 2024 - 08th June 2024
On Mohamed Raashidh Hingun, activities include excavation and backfilling, stormwater junction installation, and pipe installation. Further works involve extending and casting Stormwater junctions, foam work, road clearance, and the delivery of pipes and casting materials to the site. Deshuttering and backfilling of SW junctions, reinforcement works, and road cleaning are also underway. Materials needed for paving and pipes have been delivered to the work sites. Similarly, on Madharusa Magu, excavation and backfilling, Stormwater junction installation, pipe installation, and road clearance are in progress.
26th May 2024 - 01st June 2024
In N. Holhudhoo, significant work is being undertaken on Mohamed Raashidh Hingun. This includes extending, deshuttering, and covering storm water junctions, followed by backfilling and road clearance. The installation of storm water junctions and pipes is also in progress. Additionally, curbstones have been delivered, and previously delivered paving blocks have been relocated. Overall, the project involves extensive excavation and backfilling activities to enhance the area's infrastructure.
19th May 2024 - 25th May 2024
At Tulip Hingun, efforts are underway for the installation of curbstones and ensuring road clearance, indicative of a commitment to improving local thoroughfares. Mohamed Raashidh Hingun has seen progress in the covering and backfilling of southwest junctions, contributing to the area's overall infrastructure resilience. Meyna School has been a hive of activity, with tasks ranging from reinforcing boundary wall capping beams to completing plastering works and conducting area clearance activities, all aimed at fortifying the school's premises. Additionally, Mohamed Raashidh Hingun has been a focus for excavation, junction, and pipe installations, along with road clearance operations, further underlining the dedication to enhancing essential services. At Kaaminee Hingun, the installation of concrete tops on cable junctions underscores efforts to ensure the reliability and durability of local utilities. Lastly, attention has been directed to Tulip Hingun for excavation work related to fiber cable repair, emphasizing the importance of maintaining communication infrastructure.     
12th May 2024 - 18th May 2024
Along Mohamed Raashid Hingun, excavation and backfilling are underway, along with the installation of stormwater junctions and pipes for efficient drainage. At the same time, Tulip Hingun is seeing excavation and backfilling, curbstone installation, and the completion of stormwater junction formwork for better water management. Unimaa Magu is experiencing excavation and backfilling, along with the deshuttering of stormwater junctions to ensure smooth integration of systems. Meanwhile, Meyna School is being paved and boundary masonry work is ongoing. On Kaaminee Hingun, sinkholes are being backfilled and the road is being cleared.  
05th May 2024 - 11th May 2024
In Kaaminee Hingun, work includes the installation of stormwater foam systems, vital for managing water runoff during inclement weather, alongside area clearance initiatives. Furthermore, progress is evident in the deshuttering of stormwater junctions, a crucial step in ensuring efficient drainage systems. Over on Unimaa Magu, excavation and backfilling activities are underway, alongside the installation of stormwater junctions and pipes, enhancing the island's drainage infrastructure. At Meyna School, comprehensive groundwork is in progress, encompassing leveling, backfilling, and the meticulous casting of curbstone lines. Notably, a unique method involving the compacting of pitch using 5000 liters of seawater is being employed, underscoring innovative approaches to construction. Paving works are also in motion, promising improved accessibility and aesthetics. Lastly, along Tulip Hingun, the installation of curbstones marks another milestone in the ongoing efforts to enhance the island's thoroughfares.
28th April 2024 - 04th May 2024
Along Kaaminee Hingun, excavation and backfilling operations are laying the groundwork for forthcoming projects. The installment of stormwater junctions and pipes is progressing steadily, complemented by crucial covering and deshuttering processes to ensure durability and functionality. Concurrently, road clearance efforts are underway, alongside comprehensive pipe installations to bolster utility networks. At Meyna School, the casting of stormwater junction covers is being reinforced with ring concrete, and vital paving works are being executed to enhance accessibility.  
21st April 2024 - 27th April 2024
On Chaandhanee Hingun, preparations for stormwater junction foam work is in progress, alongside stormwater junction bar cutting, excavation, and backfilling activities. Similarly, Tulip Hingun is undergoing excavation and backfilling procedures, pipe installment, stormwater junction deshuttering, and extending works. At Meyna School, comprehensive improvements include curbstone installation, ground leveling, compacting, pipeline fixing, cleaning, and paving works. Furthermore, Kaaminee Hingun is witnessing excavation and backfilling operations, junction installment, and pipe installment activities.
07th April 2024 - 20th April 2024
Along Tulip Hingun, a flurry of activity includes excavation and meticulous backfilling, along with the installation of crucial junctions and laying and connecting of pipes. Over at Meyna School, a comprehensive overhaul is in progress, featuring the alignment of turf ground, the manufacturing and installation of a new entrance gate, and extensive excavation to facilitate drainage for the football ground. Concurrently, junctions are being installed and pipes are laid to ensure efficient water management. Meanwhile, on Chaandhanee Hingun, excavation and backfilling activities complemented by the installation of junctions and pipes. Moreover, installation of stormwater junctions is underway. 
31st March 2024 - 06th April 2024
In N. Holhudhoo, along Tulip Hingun, the construction process begins with excavation and backfilling operations, laying the groundwork for subsequent phases. Following this initial step, pipe laying and junction installment follow suit. Once the pipes are securely in place, meticulous backfilling ensues, ensuring stability and integrity for the infrastructure. Finally, road clearance activities are undertaken, prioritizing accessibility and safety for the community. This coordinated effort aims to enhance the area's infrastructure, facilitating smoother transportation and improving overall living standards.  
24th March 2024 - 30th March 2024
Construction efforts along Tulip Hingun are progressing well, with various tasks aimed at enhancing the area's infrastructure. Excavation work is currently underway to facilitate pipe laying, particularly for storm water systems and junctions. Following this, backfilling operations will be conducted to ensure the stability and functionality of the newly installed pipes.
17th March 2024 - 23rd March 2024
Various urban development projects are currently underway across different areas to enhance infrastructure and urban amenities. In Unimaa Magu, the primary focus is on improving junctions through the construction of a new one. Meanwhile, at Madharusaa Magu, efforts are directed towards clearing roads to ensure accessibility and safety for pedestrians and vehicles. In Tulip Hingun, attention is shifted to stormwater management, with ongoing excavation work for a 12-meter stormwater pipeline. Additionally, efforts are being made to clear stormwater excavation areas and backfill them, ensuring the effective management of the water drainage system.